At 7:09 a.m. on December 13, the world's largest fully automatic coal-to-gas production "Gao'an Jimin Credible Clean Energy Project" successfully trial-produced gas supply, marking that Gao'an Ceramics Base Enterprises will officially adopt "centralized supply" "gas", entering the era of clean production.
The gas is clean and stable!
The first batch of 12 ceramic companies successfully used gas for ignition
According to "Ceramic Information", the pipe network 2# of Jimin Credible (Gaoan) Clean Energy Co., Ltd. was put into trial operation that day. The first client was Jiangxi Samsung Ceramics, which achieved gratifying results of successful ignition. It was officially put into operation at 7:27. With the successful ignition of Samsung Ceramics' "coal-to-gas" project, it marks the one-time success of the trial operation of the world's largest clean gas project, marking the historic success of Gaoan Ceramics' "centralized gas supply" project and the start of high-safety production. A new chapter in cleaner production in the district.
On December 13, the first batch of 12 ceramic companies in the ceramics base have all completed ignition and put into operation, and will conduct free load gas testing for 5 days, while the second batch of companies will be held on December 16 The ignition trial operation will be carried out on the same day. Currently, Jimin Credible Clean Energy Company is following up on the gas replacement work of other users to ensure the success and stable operation of the next batch of enterprises.
Liu Chunliang, chairman of Geshiqi Ceramics, the first batch of gas testing companies, said: "Compared with corporate coal-to-gas, the clean gas produced by Jimin Credible Company this time is cleaner. According to the daily operation of the kiln, The temperature of the kiln is stable, the gas quality is stable, and the calorific value is 1,500 kcal. After the successful ignition of the gas supply, clean gas will continue to be used and will not be switched to water gas. With the stability of the gas supply, the company is most concerned about the gas supply. Price question!
Full gas supply from May 1, 2021
Previously, from December 2 to December 12, Jimin Credible Clean Gas Company carried out pipe network gas replacement for the ceramic production enterprises that were put into trial operation in the Gao'an Ceramics Park. Starting from December 13, the 36 ceramic production companies in the Gao'an Ceramics Industry Base will be divided into 3 batches. Each batch of companies will conduct a 5-day free trial production with load. The trial production for all users will be completed until March 31, 2021. Trial operation period; April 1 to April 30, 2021, is the stable operation period of gas supply.
On the starting date of the stable operation period, all production lines of all users will use clean industrial fuel.gas, and seal the two-stage furnaces of all users.
It is understood that Jimin Credible (Gaoan) Clean Energy Co., Ltd. has promised in the gas supply contract that the gas supply pressure is greater than or equal to 7kPa; the calorific value of the gas: the average calorific value is 1500kcal/m³ (in the range of 1400-1600kcal/m³ ); if the gas quality does not meet the above standards and the user's product is scrapped, the clean energy company will be responsible for compensation according to direct economic losses.
The successful commissioning of the Jimin Credible Centralized Gas Supply Project heralds that the Gao'an production area and the Gao'an ceramics industry will enter a new historical development stage. It is of milestone significance for the development of Gao'an ceramics industry. It is a milestone for the transformation and upgrading of the entire ceramics industry and even all traditional coal-using industries across the country.
(The article is reproduced from Ceramic Information)